Cistern project update

Posted on: October 29th, 2018
From:Brian@nullseedsprayers.com” <Brian@nullseedsprayers.com>
Date: October 27, 2018 at 8:52:05 PM MDT
To: RICK GEESAMAN <rcgeesaman@nullmsn.com>
Subject: Re: Gold Hill job

Rick,

Overall Good day….!
The top section got filled in and Max gave me the go-ahead to seed it all. I completed the drill seeding around all but the “base” area where the last dirt piles are.
I then got all areas covered with the erosion blanket hydro-mulch except for the last 100 feet of road and the base area.
So, for completion the base area needs to have the last of the piles removed. Max got a lot of it gone today, but there is about 1/2 of the original piles left. I can then drill and spray the last areas.
I used about 6600 gallons of water today. Was real gentle opening and closing my valve as well as the hydrant valve. I also let it drain out very well before putting the cap back on, so there should be no issues with a freeze.
If the community asks… the green mulch color fades in a few days, and everything used is plant based, 100% biodegradable, and completely safe for humans and animals, etc.

Thanks,
Brian